Column Leach Tests Confirm Rare Earths Heap Leach Potential
Released
Released
Announcement PDF
For more information, please join ABx Group’s interactive Investor Hub
ABx Group Limited
Suite 2, Level 11, 385 Bourke St, Melbourne VIC 3000, Australia
ABN 14 139 494 885 |P: +61 3 9692 7222 | F: +61 2 9956 7355
Column Leach Tests Confirm Rare Earths Heap Leach Potential
Engage with this announcement on our interactive Investor Hub
Preliminary column leach results from ANSTO on 26 kg bulk samples
demonstrate very high extraction of high-value heavy rare earths
Results support the technical feasibility of heap leaching for the Deep Leads
ionic adsorption clay rare earth project
Final column leach performance to be confirmed following column unloading in
early January
ABx Group Limited (ASX: ABX) (ABx or the Company) is pleased to report outstanding
preliminary results from two rare earth column leach tests conducted on 26 kg bulk samples
by the Australian Nuclear Science and Technology Organisation (ANSTO), as part of ongoing
metallurgical studies at the Deep Leads rare earth project in northern Tasmania.
After 17 days, the first column test has achieved 81% extraction of rare earths, including 76%
extraction of dysprosium (Dy) and 79% extraction of terbium (Tb), which are two of the
highest value rare earths. The second column test is nearing completion.
ABx has previously reported results from a series of short-duration leaching tests on sub-
samples from a bulk sample taken from the Deep Leads resource and consistently achieved
65-75% extraction.1
This record high 81% extraction from the column leach test is the best
results achieved in large scale tests from any Australian clay-hosted rare earth deposit and
shows that ABx’s ionic clay rare earths are especially suited to low cost heap leaching.
The maiden mixed rare earth carbonate (MREC) product that was recently produced from a
similar bulk sample was twice as enriched in Dy and Tb compared to any peer MREC, and
had a basket price 17% to 51% higher than all peer MRECs.2
ABx Group Managing Director and CEO Dr Mark Cooksey said:
“These preliminary column leach results are extremely encouraging. Achieving very high
extractions of the most valuable and important heavy rare earths such as dysprosium and
terbium, while maintaining very low impurities, strongly supports the potential for heap leaching
at Deep Leads.
“Heap leaching potentially offers a compelling pathway to lower capital intensity, consistent with
the ABx strategy to commence commercial production as soon as possible.”
1
ASX Announcement, 17 September 2025
2
ASX Announcement, 2 December 2025
ASX Announcement
18 December 2025
ASX: ABX
ASX announcement 18 December 2025
page 2
Figure 1: Column leach tests in progress at ANSTO on 26 kg samples from the ABx Deep Leads deposit
Bulk Sample Material
The source material for the column leach tests was a bulk sample from trial pit DLP002 from
the Deep Leads resource (Error! Reference source not found.1).3
A fresh 100kg (wet) sub-
sample was obtained by homogenisation and fractional shovelling on a tarp followed by light
disaggregation and hand-screening at 10mm. Manually identified clasts (<5% of sample)
were removed by hand.
Purpose of Column Leach Tests
3
ASX Announcement, 6 August 2025
ASX announcement 18 December 2025
page 3
In tank leaching, the clay ore is added to tanks containing an ammonium sulfate solution.
The tanks are stirred to produce a slurry, which ensures good contact between the ore and
the ammonium sulfate. The rare earths are desorbed from the clay into the sulfate solution.
Heap leaching involves forming a heap of clay ore on an impermeable, gently sloping pad
and irrigating from above with leachate. The leachate percolates downward through the
heap and extracts rare earths into solution. The enriched solution is collected at the base.
Heap leaching is potentially lower capital cost than tank leaching, because less capital
equipment is required.
Column leach tests are a good simulation of a heap leach. The column leach tests reported
here are to determine whether the leaching performance in column tests is any different to
that previously obtained in tank leaching tests, and they indicate the likely heap leaching
performance.
Column Leach Test Details
• Ore was homogenised and screened at 10 mm, followed by agglomeration to a
10 mm feed to consolidate fines and ensure suitable bed structure and permeability
• Two identical columns, each 2.4 metres high and 150 mm in diameter (Figure 1)
• Approximately 26 kg of ore per column to a ‘bed height’ of 2m
• Two ammonium sulfate leachate concentrations:
o Test 1: 0.30 M ammonium sulfate
o Test 2: 0.15 M ammonium sulfate
• Irrigation rate of ore with leachate: 5.0 L/m²/hour (approximately 2.12 L / day)
• Ambient temperature (~21°C)
• Target pH: 4.0 (actual feed pH ~3.8)
Importantly, both columns demonstrated very low impurity dissolution, including minimal
aluminium, reinforcing previous findings that Deep Leads mineralisation can deliver high-
purity rare earth solutions using benign chemistry. Additionally, both columns exhibited
excellent physical characteristics of bed stability and percolation.
Next Steps
The column leach tests will complete as planned before the end of December and be
unloaded in early January. The solid residues and remaining solutions will be analysed to
determine final rare earth recoveries, impurity levels and assess leaching kinetics.
Final results from the column leach program will be reported once analysis is complete.
Given the strong customer interest in MRECs from the Deep Leads resource, ABx is
considering engaging ANSTO to produce another MREC sample from the rare earth rich
solution produced from these column leach tests.
ASX announcement 18 December 2025
page 4
This announcement is approved for release by the board of ABx Group Limited.
Go to the ABx Investor Hub to watch a video of this announcement and ask any questions of
management.
For further information please contact:
Dr Mark Cooksey
MD & CEO
ABx Group
+61 447 201 536
mcooksey@abxgroup.com.au
www.abxgroup.com.au
Media
Chapter One Advisors
David Tasker / Alex Baker
+61 433 112 936 / +61 432 801 745
dtasker@chapteroneadvisors.com.au /
abaker@chapteroneadvisors.com.au
About ABx Group Limited
ABx Group Limited (ABx) is a uniquely positioned Australian company delivering materials
for a cleaner future.
The three priority projects are:
• Heavy rare earths: Supplying light and heavy rare earths from Tasmania into
Western supply chains
o Maiden mixed rare earth carbonate produced
o Processing Options Analysis conducted in partnership with external experts
• Clean fluorine chemical production: Producing industrial chemicals from
aluminium smelter by-product (ALCORE)
o Continuous pilot plant under construction in Bell Bay, Tasmania
• Near-term bauxite production: Mining bauxite resources for the aluminium,
cement and fertiliser industries
o Agreements executed with Good Importing International for bauxite projects
in Queensland and New South Wales, and $2.7 million initial payment has
been received
o Approvals well advanced for DL130 bauxite project in northern Tasmania
ABx endorses best practices on agricultural land and strives to leave land and environment
better than we find it. We only operate where welcomed.
Disclaimer Regarding Forward Looking Statements
This ASX announcement (Announcement) contains various forward-looking statements. All
statements other than statements of historical fact are forward-looking statements.
Forward-looking statements are inherently subject to uncertainties in that they may be
affected by a variety of known and unknown risks, variables and factors which could cause
ASX announcement 18 December 2025
page 5
actual values or results, performance, or achievements to differ materially from the
expectations described in such forward-looking statements.
ABx does not give any assurance that the anticipated results, performance, or achievements
expressed or implied in those forward-looking statements will be achieved.
Competent Persons Statement
The information in this report that relate to Exploration Information and Mineral Resources
are based on information compiled by Ian Levy who is a member of The Australasian
Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr Levy is a
qualified geologist and a director of ABx Group Limited.
Mr Levy has sufficient experience, which is relevant to the style of mineralisation and type of
deposit under consideration and to the activity, which he is undertaking to qualify as a
Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of
exploration Results, Mineral Resources and Ore Reserves. Mr Levy has consented in writing
to the inclusion in this report of the Exploration Information in the form and context in which
it appears.
Table 1 - Summary of sampling information referred to above, in accordance with LR 5.8.1
Geology and geological interpretation REE mineralisation occurs in clay layers that overlie a Jurassic age dolerite
basement in a district with some residual weathered Tertiary age alkali
basalt.
Sampling and sub-sampling techniques Pit sampling was done at 1 metre intervals using a large excavator with an 8
metre boom.
Subsampling of ~100kg was performed by fractional shovelling. This sample
was lightly disaggregated and hand-screened at 10mm without drying.
Drilling techniques Not applicable (N.A.). Bulk pit sampling by excavator
Criteria usedfor resource classification, drill&
data spacing & distribution.
N.A.
Sample analytical method Assay samples are analysed by standard NATA-approved induction coupled
plasma analytical methods for rare earth elements at ALS labs in Brisbane
(method ME-MS81). Interlab comparisons were satisfactory.
Estimation methodology, cut-off grade,
mining, metallurgy & other modifying
factors
All N.A.
JORC Code, 2012 Edition – Table 1
Section 1 Sampling Techniques and Data
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling
• Include reference to measures taken to ensure sample
representivity
• Aspects of the determination of mineralisation that are
Material to the Public Report.
• Industry standard work:
• Bulk pit dug by excavator
• Samples taken at 1 metre intervals by
cleaning pit at the metre interval, then
taking full 1 metre slice for the samples.
• Subsampling the metre samples done as per
ISO bauxite sampling processes
Drilling
techniques
• Drill type • Not applicable to bulk pits excavated by
excavator with 8 metre boom
ASX announcement 18 December 2025
page 6
Criteria JORC Code explanation Commentary
Drill sample
recovery
• Method of recording and assessing core and chip sample
recoveries and results assessed.
• Not applicable to bulk pits
Logging • Whether samples have been geologically and geotechnically
logged to an appropriate level for metallurgical studies.
• Whether sampling is qualitative or quantitative.
• Totallength&percentageoftherelevantintersectionslogged.
• Pits sampled, assayed, logged, photographed &
& stored to ISO standards. See below
• All8metreswasloggedandsampled
• Depth 5m to 6m selected – see below
Sub-
sampling
techniques
andsample
preparation
• If core, whether cut or sawn, quarter, half or all core.
• If non-core, sample method, whether sampled wet or dry.
• Nature, quality & appropriateness of the sample preparation.
• Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.
• Measures taken to ensure that the sampling is representative
of the in situ material collected, including for instance results
for field duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the
material being sampled.
• Depth 5m to 6m selected for the sample to
be used to produce a mixed carbonate rare
earth carbonate (MREC)
• 100kg sub-sample obtained by
homogenisation and fractional shovelling on
a tarp followed by light disaggregation and
hand-screening at 10mm. Manually
identified clasts (<5% of sample) were
removed by hand.Separatesubsamples
assayedthesame
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.
• Geophysical tools, spectrometers, handheld XRF instruments,
etc, the parameters used in determining the analysis
• Nature of quality control procedures adopted.
• Assaying done by NATA-registered ALS
laboratories, Brisbane
• N.A. Assays are by ALS which is a major
mineral laboratory
• ALS is industry-standard and publishes its
QA/QC protocols and results on its website
Verification
of sampling
and
assaying
• The verification of significant intersections by either
independent or alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Pit sampling supervised by 4 ABx senior staff
– see Competent Person & Expert
Statement for details.
• Repeated subsampling assayed the same.
• Metal assays from ALS converted to oxides
as per industry standards for reporting
Location of
data points
• Accuracy & quality of surveys used to locate drill holes & pits.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• Location by GPS
• Pit DLP002 location: 477720E , 5410126N
(WGS 84 56S grid). RL 287.675m by LiDAR.
Data
spacing and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient.
• Whether sample compositing has been applied.
• Bulk pit sampling at 1m intervals considered
appropriate and sufficient
Orientationof
datainrelation
togeological
structure
• Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which this is
known, considering the deposit type.
• Does the drilling orientation introduce a sampling bias
• Vertical bulk pit sampling is appropriate for
the horizontal layers of REE mineralisation
Sample
security
• The measures taken to ensure sample security. • Chain of custody protocols were applied to
secure the bulk bag samples.
Audits or
reviews
• The results of any audits or reviews of sampling techniques
and data.
• Two bulk samples taken simultaneously
assayed the same