ALCORE Pilot Plant Progress
Released
Released
Announcement PDF
ASX Announcement
21 June 2023
ASX: ABX
ALCORE Pilot Plant Preliminary Engineering Design
Complete, Advanced Laboratory Reactor Ordered
ALCORE preliminary engineering design completed for pilot plant facility. Detailed
engineering design underway
ALCORE Technology Centre site preparation underway, with contractor discussions
commenced for civil and electric works
Advanced laboratory reactor ordered, with delivery anticipated in Q3 CY2023
Figure 1 – Current ALCORE laboratory-scale reactor
ABx Group (ASX: ABX) (“ABx” or “the Company”) is pleased to provide an update on its 83%owned subsidiary ALCORE Limited (ALCORE), which has recently completed the preliminary
engineering design phase for its rapidly advancing pilot facility and also ordered a significant
laboratory reactor.
ALCORE is developing a pilot plant in NSW to recover fluorine from ‘excess bath’ (an
aluminium smelter waste product) to produce hydrogen fluoride, with a later-stage
commercial plant to further react the hydrogen fluoride to produce aluminium fluoride – a
high-value chemical essential for aluminium smelting.
ABx Group Limited
Level 5 52 Phillip Street Sydney NSW 2000
ABN 14 139 494 885
P: +61 2 9251 7177
F: +61 2 9251 7500
ASX release 21 June 2023
page 2
Commenting on the progress made by ALCORE, ABx Group Managing Director and CEO Mark
Cooksey said:
“It is exceptionally pleasing to see progress accelerating at ALCORE. The Company has the
opportunity to solve an increasing waste issue for global aluminium smelters, while also producing
a necessary smelting additive, which is not only high-value but, for many countries including
Australia, is subject to significant supply risks.
“The completion of the preliminary engineering design and order of a crucial laboratory bath
reactor are two major milestones towards demonstrating the process at pilot scale. The pilot plant
remains on track to be constructed by end CY2023”
The main purpose of the preliminary engineering design phase is to specify the major design
and operating parameters for the significant components of the pilot plant.
The Company has now finalised plant capacity and general layout, comprehensive process
flow, piping and instrumentation diagrams, raw material storage and waste management
plans, process safety and control philosophies, and sizing of major equipment.
Its completion now permits the Company to conduct the detailed engineering design of the
pilot plant, in partnership with several engineering suppliers, including specialist overseas
manufacturers. Meanwhile, ALCORE is progressing site preparation works with the pilot
facility to utilise space at the ALCORE Technology Centre in Berkeley Vale, Central Coast NSW.
As part of these preparatory works, ALCORE has entered discussions with contractors for
civil and electric infrastructure work. Additionally, the Company is also progressing all
necessary permits and approvals with local authorities.
Milestone Laboratory Reactor Order
ALCORE has further cemented its pilot plant development pathway with the order of an
advanced laboratory reactor for enhanced processing of excess bath material.
The Company has been reacting sulfuric acid (oleum) with bath to recover fluorine at a
laboratory-scale (Figure 1) and with initial operating conditions identified1, the pilot plant will
seek to evaluate these conditions at greater scale.
The feed materials must be intimately mixed during the reaction to maximise the
consumption of feed materials and quality of final products. These are important for process
economics and customer acceptance.
The earlier results at laboratory-scale were limited by extent of process mixing that could be
achieved. Pleasingly, in early 2023, ALCORE identified an international supplier that could
manufacture a reactor which employs state-of-the-art technology to enhance process
mixing, which is critical to achieving high fluorine yield.
1
See ASX Announcement dated 24 October 2022
ASX release 21 June 2023
page 3
Following further due diligence, the reactor technology has been determined to be highly
advantageous for ALCORE with an order now placed.
Delivery at the ALCORE Technology Centre is anticipated to occur in Q3 CY2023.
Following successful delivery and installation, experiments are to be conducted on this
reactor in parallel with pilot plant construction.
These experiments will include confirmatory work on ALCORE’s selected range of process
conditions, with the improved reactor anticipated to deliver greater yields. These results
should enable tests on the pilot plant to be even more effective.
This announcement is approved for release by the board of directors.
For further information please contact:
Dr Mark Cooksey
MD and CEO
ABx Group
Mobile: +61 447 201 536
Email: mcooksey@abxgroup.com.au
Website: abxgroup.com.au
Disclaimer Regarding Forward Looking Statements
This ASX announcement (Announcement) contains various forward-looking statements. All
statements other than statements of historical fact are forward-looking statements. Forward-looking
statements are inherently subject to uncertainties in that they may be affected by a variety of known
and unknown risks, variables and factors which could cause actual values or results, performance, or
achievements to differ materially from the expectations described in such forward-looking
statements.
ABx does not give any assurance that the anticipated results, performance, or achievements
expressed or implied in those forward-looking statements will be achieved.